Memory — still rising in Q4, at different rates by product

TrendForce (September 30) expects conventional DRAM contract prices to rise 10–15% QoQ in 4Q26 and NAND Flash 15–20%, after 3Q26 forecasts of 13–18% and 10–15%. Server DRAM remains undersupplied, although long-term agreement (LTA) pricing may keep some suppliers' increases below the market average; mobile and consumer DRAM keep rising at a slower pace, and enterprise SSD is the only category expected to see larger gains than last quarter. Legacy and specialty memory is tighter: TrendForce estimates average contract prices rose 130–150% for SLC NAND and 100–120% for NOR Flash in 1H26, with SLC NAND able to rise another 70–75% on average in 2H26. It also reports some OEMs moving DDR4 designs to DDR3 and DDR3 designs to DDR2

Supplier results point the same way. Micron reported fiscal Q4 2026 revenue of $54.23 billion (prior quarter $41.46 billion; a year earlier $11.32 billion) and guided $61.5 billion ± $1.5 billion for the next quarter. SK hynix said in July that customer demand exceeds supply; its Q3 results are due on October 28 and are not covered here

Sources [1][2][3][4][5][6][7]

SEUNGJUN’s take — what to do now

Re-check your memory requirements through the first half of 2027 now, and move firm quantities into quote requests early. For products built on legacy parts such as DDR3, DDR4, SLC NAND or e.MMC, watch EOL and PCN notices and evaluate other densities or alternative specifications in advance. Prices are changing quarter by quarter, so check the validity period of every quote; SEUNGJUN can confirm item-level lead times for SK hynix, SkyHigh Memory and ATP products through a quote request

Lead times — pressure that began in memory now reaches every category

In ECIA's September Industry Pulse survey, the share of respondents reporting increasing semiconductor lead-time pressure rose from 72% in August to 77%; for passives and electro-mechanical components it eased but stayed at 61–63%, with none reporting declining pressure. ECIA notes that the pressure is felt across all product categories, not just DRAM and data flash. Its overall component index rose from 136.7 to 142.0, and the semiconductor index is expected to reach 150.0 in October

Memory remains the tightest: TrendForce says DRAM suppliers are prioritizing advanced-process capacity for high-performance server products, and legacy SLC NAND and NOR Flash face a risk of prolonged shortages in long-lifecycle automotive and industrial products. Standard MLCCs are relatively stable at 14–18 weeks, while high-capacitance and high-voltage parts are at 15–20 weeks and some reach around 40 weeks (TrendForce, citing ETNews). TrendForce expects a major MLCC supplier to raise 4Q26 OEM/ODM prices by an average of 25–30% for consumer-grade X5R and 10–20% for AI-server X6S parts

Sources [1][3][8][9][10]

SEUNGJUN’s take — what to do now

Review your BOM by part number rather than by category average, and confirm first-half 2027 requirements early for parts with long lead times or allocation. Evaluating and approving pin-compatible alternatives, other packages or second-source parts in advance gives you room to respond if allocation hits. Ask SEUNGJUN for item-level lead times through a quote request

Exchange rate — the won firms against the dollar, with wider daily swings

According to the Bank of Korea (October 16), the won/dollar rate (Seoul interbank close) was 1,424.0 at the end of July, 1,368.6 at the end of August, 1,352.8 at the end of September and 1,338.3 on October 14 — a 2.3% rise in the won's value since end-August. The rate first rose on Middle East uncertainty and expectations of Fed rate hikes, then fell as exporters sold more dollars, even as the dollar index (DXY) rose from 99.4 to 102.6. The average daily move widened to 7.0 won (0.52%) in September from 4.4 won (0.31%) in August

Monthly averages fell from 1,488.9 in July to 1,404.4 in August and 1,358.8 in September; the Q3 average was 1,418.6, down from 1,501.6 in Q2. On the Bank of Korea's ECOS daily data, the October 20 close was 1,328.1. A stronger won has partly offset dollar price increases for Korean buyers, but wider daily swings make the gap between quote date and payment date matter more

Sources [11][12]

SEUNGJUN’s take — what to do now

For parts paid in US dollars, build the exchange-rate gap between quote date and payment date into your budget. When daily swings widen, spreading orders and payments over time rather than bunching them is one way to reduce risk. Exchange-rate forecasts differ from one institution to another, so review your internal reference rate regularly

Sources

Figures are as stated by each source on its reference date. Outlooks are the sources’ forecasts, not certainties. For item-level prices and lead times, send us a quote request

  1. [1] TrendForce · AI Server Demand Sustains Memory Contract Price Increases in 4Q26, While Consumer-Side Pressure Persists (opens in a new tab) PublishedSeptember 30, 2026 · Checked October 21, 2026
  2. [2] TrendForce · AI Server Demand Continues to Support Memory Prices in 3Q26, but Gains Moderate as Consumer Demand Weakens and High Base Effects Take Hold (opens in a new tab) PublishedJuly 3, 2026 · Checked October 21, 2026
  3. [3] TrendForce · Contract Prices Surged More Than 100% in 1H26; Structural Shortages to Keep NOR Flash and SLC NAND Prices Rising in 2H26 (opens in a new tab) PublishedJune 16, 2026 · Checked October 21, 2026
  4. [4] TrendForce · Consumer DRAM Shortages Extend to DDR2 Products with Contract Prices Expected to Continue Rising in 3Q26 (opens in a new tab) PublishedJune 22, 2026 · Checked October 21, 2026
  5. [5] Micron Technology · Micron Technology, Inc. Reports Record Fiscal Fourth-Quarter and Full-Year 2026 Results (opens in a new tab) PublishedSeptember 30, 2026 · Checked October 21, 2026
  6. [6] SK hynix Newsroom · SK hynix Q2 2026 business results (opens in a new tab) PublishedJuly 29, 2026 · Checked October 21, 2026
  7. [7] SK hynix Newsroom · Q3 2026 Earnings Conference Call Invitation (opens in a new tab) PublishedOctober 21, 2026 · Checked October 21, 2026
  8. [8] ECIA · Industry Pulse: Electronic Component Trends and Sentiment, September 2026 — Executive Summary (opens in a new tab) PublishedOctober 1, 2026 · Checked October 21, 2026
  9. [9] TrendForce News · MLCC Lead Times Diverge as High-End Products Stretch to 5–10 Months; Tightness May Extend Into 2027 (opens in a new tab) PublishedAugust 18, 2026 · Checked October 21, 2026
  10. [10] TrendForce · SEMCO Leads 4Q26 OEM Price Hikes, Signaling Start of MLCC Industry Upcycle (opens in a new tab) PublishedAugust 27, 2026 · Checked October 21, 2026
  11. [11] 한국은행 · 2026년 9월 이후 국제금융·외환시장 동향 (opens in a new tab) PublishedOctober 16, 2026 · Checked October 21, 2026
  12. [12] 한국은행 경제통계시스템(ECOS) · 원/달러 환율(종가 15:30) 일별 — 2026년 10월 20일 값까지 (opens in a new tab) Checked October 21, 2026